Precautions for operating JS concrete mixer after shutting down the machine
February 14, 2024
1.The staff should close the bulk cement tank gate after the use of concrete mixer is completed on the same day, and convey all the cement in the spiral pipe, and do not leave any cement in the pipe. At the same time thoroughly clean the machinery and the site.
2. The concrete in the mixing drum of the concrete mixer must be cleaned. Maintenance of machinery, lubricating oil for each lubrication point, the need to protect the part of the oil rust.
3.Clean the slurry and accumulated dust in all parts of the forced mixer. Clean the dust, concrete and oil on the surface of the mixing tank and the whole machine in a timely manner to prevent the concrete from drying out and keep it clean. At the end of production, thoroughly clean the concrete remaining in the mixer before stopping the machine. After stopping the machine, place all operating switches in the disconnected position and turn off the power switches.
some customers think that forced mixer completion as long as the shutdown on the line, in fact, this idea is wrong, in order to eliminate concrete mixer safety hazards in a timely manner, to ensure that the mixer state is intact, so after the shutdown should be very good maintenance, will not be frequent occurrence of a number of minor problems. Here Zhengzhou Xinfeng machinery tell you only to comply with the reasonable use and maintenance of JS concrete mixers in order to extend the life and let you work at ease to improve efficiency.
concrete mixer for concrete batching plant